JAHRA DISTRICT CONTROL CENTRE

At the beginning of 1993, the Ministry of Electricity and Water issued Tender No. C / 1960 - 87 - 88 whose content was to build the Jahra Control Center and carry out the complete civil works. This project includes constructing buildings, offices, agricultural works (the garden), and the power station.

The bid was awarded to Coglix Alstom Company as the main contractor and Ali Al Sayegh Contracting Company as a contractor for civil works because our company has a distinguished history in construction and construction and speed in implementation with complete accuracy, skill, expertise, and approvals from most of the state ministries that our company has.

Also, this project consists of the main building, which contains a control room comprised of two floors and a giant screen showing all the electricity stations inside this building for easy automatic control. The project also contains internal roads, fences, parking shades, landscaping, and planting works.

The project was completed in record time, taking into account the factor of quality and accuracy in implementation we were evaluated with a degree of excellence in implementation, This building is the fourth control center for all Kuwait power stations, and it is concerned with substations in the Jahra area and its suburbs.

PROJECT NAME : JAHRA DISTRICT CONTROL CENTRE

LOCATION : KUWAIT - JAHRA

CLIENT : "M.E.W. COGELEX ALSTHOM"

NAURATION : CONTRACT NO.ENP-C/1960-87/88

DATE OF COMPLATION : 1993

POWER & ENERGY